Cs615
Assignment Idea Solution
· You are in the process of Source Selection
for a contract for your project. You are planning to use weighing process for
source selection. There are four vendors being considered. There are two
deciding factors price (weightage 40), quality (weightage 60). The scores of
four vendors that your team has computed are displayed in the table below.
Which vendor will among these four should be chosen?
Vendor scores |
| Vendor 1 | Vendor 2 | Vendor 3 | Vendor 4 |
Price | 8 | 10 | 12 | 11 |
Quality | 12 | 10 | 8 | 11 |
- Vendor 1
- Vendor 2
- Vendor 3
- Vendor 4
- We
need to compute the following for all the vendors - (0.4*Price +
0.6*Quality). The scores come out to be vendor 1 - 10.4, vendor 2 - 10,
vendor 3 - 9.6, and vendor 4's 11. Since vendor 4 has the highest score,
it should get selected.
· You are the Project Manager for XYZ project.
The scope of the project has been completed. You receive a request for a new
module to be developed as part of this project. What should you do next?
- You should approach the
Project sponsor and ask her for a new module to be developed as part of
this project.
- You should approach the
Senior Management and ask them for a new module to be developed as part of
this project.
- You should send the request
to Change Control Board for approval.
- Since the project scope is
completed you should inform the customer that this change cannot be done
as part of the project.
Answer:
d. As the scope is completed, the project is complete.
Additional work should be done as part of a new project.